Millennium Team was the main contractor on the drainage and excavation projects that preceded the construction of all the facilities in Belgrade Waterfront.
In the course of those projects, over 960,000 m3 of soil was excavated and the amount of groundwater eliminated by drainage systems during the construction of facilities on the plots of Belgrade Waterfront is over 1,200,000.00 m3.

Location

Belgrade

Employer

Beograd na vodi d.o.o.

Type of Service

Execution of earth works

Period/Status

2016-2022; Finished.