Gasification of city municipality Zemun

This project includes the construction of a 25 km of steel medium-pressure gas pipeline, as well as the construction of a distribution gas pipeline using polyethylene pipes with a total length of 470 km and the construction of 10 metering and regulating stations.

Location

Municipality of Zemun, Belgrade

Employer

PE Srbijagas Novi Sad

Type of Service

Construction of gas pipeline network and MRS

Period/Status

In progress;
The total length of the network constructed so far is over 425 km.

„Turkish stream“ Section 1 – Finished earth works